Clarabelle Mill in Sudbury, Ontario, processes ore from Vale’s nickel and copper mines in the surrounding area. Its size-reduction operations include semi-autogenous grinding (SAG), rod and ball mills. In 2018, Vale approached Endurance Belting for a specialized steelcord belt for the site. The request combined a technical challenge in belt troughing with an urgent need for delivery to the operation.
The conveyor’s steep idler angles had historically created troughing issues for the belting. Vale needed a configuration that addressed this geometry while providing reinforcement for the ore-handling duty. Abrasion resistance and rip protection were also identified in the project specification. The task required attention to how the belt would form into the conveyor trough, alongside its tensile construction and protective features. Quick delivery was also an immediate priority for the customer.

Endurance worked with Vale to develop a steelcord belt with transverse steel breakers for the application. The Endurasteel Plus construction incorporated an elastic steelcord breaker within the top cover. This transverse reinforcement adds lateral strength and is designed to help absorb impact loads and resist puncture, ripping and rip propagation. The specified belt was 1067mm wide and ST2000 rated, with 12 mm × 7 mm covers. 2,400m of the belt was installed in the project. The configuration brought together the steelcord carcass and protective reinforcement around the site’s stated requirements.